PennDOT Roadwork Schedule

Starting the week of July 26, 2021 you should begin to see material and equipment dispersed throughout the township. Tar and chip roadwork will take place starting at the bin site on Skelp Mountain Rd with work moving from Skelp Mountain Rd to Golf Course Rd, then Kettle Rd to I-99 Bridge and back to Rt 453, then to Hileman Rd, Silver Barn Rd, Quarry Rd, and back Skelp Mountain Rd to the bin site. These dates are all weather permitting. Signs will be posted prior to work beginning.

As always, please maintain slow, safe driving speeds in the work zone to maintain the safety of road workers!